PROJECT OVERVIEW

Façade and balcony fire safety remediation

Project
Island Gardens (Equinox)
Location
1 Douglas Path, London E14 3GR
Department
Principal Contractor & BSR ↗
Building
Two interconnected residential blocks · Ground + six upper floors
Accommodation
84 residential units and ground-floor commercial space
Highest occupied floor
17.54 m above ground
Conex role
Building Regulations Principal Contractor, as recorded in the Construction Control Plan

Conex Limited prepared a Construction Control Plan for the proposed fire safety remediation of the Island Gardens (Equinox) development. The plan sets out a coordinated approach to external wall remediation, balcony upgrades, regulatory compliance, construction quality and resident safety in an occupied higher-risk building.

Following façade fire risk assessment and technical review, the planned works address combustible EPS-insulated render, PIR-cored aluminium spandrel and infill panels, and timber balcony decking. The specified replacements include mineral wool insulated render, non-combustible aluminium panel and decking systems, and new cavity fire barriers at critical junctions.

The project documentation identifies the building as a higher-risk building and establishes procedures to support Gateway 2 submission, construction-stage change control and Gateway 3 evidence. The October 2025 plan does not establish that remediation has been completed or regulatory approval granted.

PROJECT DELIVERY APPROACH

Coordinated remediation.
Traceable building safety.

Proposed controls designed around occupied-building access, fire safety interfaces and evidence-led quality assurance.

01

Non-combustible façade systems

Replace specified EPS render with A2-s1-d0 mineral wool insulated render, and PIR-cored panels with non-combustible assemblies.

02

Balcony and fire barrier upgrades

Replace timber balcony decking with aluminium systems, inspect structural fixings and install vertical and horizontal fire barriers.

03

Occupied-building management

Resident liaison, safe scaffold access, weather protection, controlled waste removal and maintained live services.

04

Inspection and golden-thread records

Inspection and test plans, concealed-work photographs, product batch traceability, change control and as-built handover evidence.